HC upholds Rera relief for Gaur City Centre shop buyers
Noida: The Lucknow bench of Allahabad High Court has dismissed four appeals filed by Gaursons Hi-Tech Infrastructure over shop-buyer disputes at its Gaur City Centre project in Greater Noida West, refusing to interfere with orders passed in the favour of buyers by UP-Rera and Real Estate Appellate Tribunal (REAT).The court declined to condone delays in approaching it, holding that the developer failed to show reasonable diligence through the litigation and that the reasons offered were "bald, unsupported and unsatisfactory", in some instances reflecting a "careless and reckless" approach. The decision now clears the way for execution of Rera orders.
In a set of judgments delivered on Jan 21, Justice Prashant Kumar held that limitation cannot be relaxed as a matter of generosity and that courts must separate a genuine explanation from a mere excuse. The court relied on multiple Supreme Court rulings to underline that repeated, unexplained delays and laches cannot be overlooked.The four cases are the result of complaints filed by allottees who booked commercial units at Gaur City Centre in Sector 4 of Greater Noida West. Under these plans, buyers paid 30-50% of the total consideration upfront, with the bulk amount linked to the offer of possession.When possession was not offered within the promised timelines, the allottees approached UP-Rera between 2021 and 2022. Rera conducted spot inspections and found construction at the project incomplete. It then asked the developer to complete construction in line with the agreements, obtain occupancy certificates, hand over possession, execute sale deeds, and pay interest for delayed possession at prescribed rates, subject to adjustment of any buyer overdues.Gaursons challenged the Rera directions before REAT in Lucknow. However, each appeal was dismissed on the ground of delay and laches, with delays ranging from 79 to 224 days. The tribunal passed separate dismissal orders during Oct-Nov 2024.REAT also recorded non-compliance with the mandatory pre-deposit requirement under the Rera Act. It rejected the developer's explanation that the delay was caused by difficulty in retrieving electronic records due to malware, noting that relevant documents were available on the Rera web portal.The developer then moved High Court, again with the delayed filings. Dismissing all four appeals as barred by limitation, the court said the pattern of delay showed a lack of diligence that could not be excused. "...the appellant failed to prove that he was reasonably diligent in pursuing the matter not only before this Court but also before the UP Real Estate Appellate Tribunal, Lucknow," the court noted, adding that such conduct disentitles a litigant from discretionary relief.With HC refusing to intervene, the dismissal effectively removes the appellate roadblock and allows the buyers to pursue execution of the Rera orders.A Gaursons spokesperson said the company had challenged the REAT order primarily on the interpretation of "deemed completion". "The primary issue concerns the interpretation of ‘deemed completion', which, as consistently submitted by the company, stands fully satisfied in the present project. The applicable bylaws expressly recognise deemed completion upon the expiry of three months, provided the statutory requirements are fulfilled. This position was also acknowledged by UP-Rera through its notification dated Sept 16, 2019, which recognises the concept of a deemed occupancy/completion certificate. In the present case, all 4 mandatory no objection certificates were duly obtained and remained valid during the relevant period," the spokesperson said.On the delays, the spokesperson added: "The company further submitted that the delay in filing occurred solely due to an unforeseen technical issue in retrieving electronic data from the relevant systems, which temporarily hindered the compilation of documents. The delay was entirely unintentional and does not reflect any lack of diligence or improper conduct on the part of the company."
In a set of judgments delivered on Jan 21, Justice Prashant Kumar held that limitation cannot be relaxed as a matter of generosity and that courts must separate a genuine explanation from a mere excuse. The court relied on multiple Supreme Court rulings to underline that repeated, unexplained delays and laches cannot be overlooked.The four cases are the result of complaints filed by allottees who booked commercial units at Gaur City Centre in Sector 4 of Greater Noida West. Under these plans, buyers paid 30-50% of the total consideration upfront, with the bulk amount linked to the offer of possession.When possession was not offered within the promised timelines, the allottees approached UP-Rera between 2021 and 2022. Rera conducted spot inspections and found construction at the project incomplete. It then asked the developer to complete construction in line with the agreements, obtain occupancy certificates, hand over possession, execute sale deeds, and pay interest for delayed possession at prescribed rates, subject to adjustment of any buyer overdues.Gaursons challenged the Rera directions before REAT in Lucknow. However, each appeal was dismissed on the ground of delay and laches, with delays ranging from 79 to 224 days. The tribunal passed separate dismissal orders during Oct-Nov 2024.REAT also recorded non-compliance with the mandatory pre-deposit requirement under the Rera Act. It rejected the developer's explanation that the delay was caused by difficulty in retrieving electronic records due to malware, noting that relevant documents were available on the Rera web portal.The developer then moved High Court, again with the delayed filings. Dismissing all four appeals as barred by limitation, the court said the pattern of delay showed a lack of diligence that could not be excused. "...the appellant failed to prove that he was reasonably diligent in pursuing the matter not only before this Court but also before the UP Real Estate Appellate Tribunal, Lucknow," the court noted, adding that such conduct disentitles a litigant from discretionary relief.With HC refusing to intervene, the dismissal effectively removes the appellate roadblock and allows the buyers to pursue execution of the Rera orders.A Gaursons spokesperson said the company had challenged the REAT order primarily on the interpretation of "deemed completion". "The primary issue concerns the interpretation of ‘deemed completion', which, as consistently submitted by the company, stands fully satisfied in the present project. The applicable bylaws expressly recognise deemed completion upon the expiry of three months, provided the statutory requirements are fulfilled. This position was also acknowledged by UP-Rera through its notification dated Sept 16, 2019, which recognises the concept of a deemed occupancy/completion certificate. In the present case, all 4 mandatory no objection certificates were duly obtained and remained valid during the relevant period," the spokesperson said.On the delays, the spokesperson added: "The company further submitted that the delay in filing occurred solely due to an unforeseen technical issue in retrieving electronic data from the relevant systems, which temporarily hindered the compilation of documents. The delay was entirely unintentional and does not reflect any lack of diligence or improper conduct on the part of the company."
You Can Also Check: Noida AQI
|
Bank Holidays in Noida |
Gold Rate Today in Noida |
Silver Rate Today in Noida
Popular from City
- How Confident Group chairman CJ Roy’s final hours unfolded at his Bengaluru office amid Income Tax searches: ‘He kept his briefcase with pistol and documents always close to him’
- Jhanvi Kukreja murder on New Year's Eve: Accused Shree Jogdhankar convicted; co-accused Diya Padalkar acquitted
- From bricks to blockbusters: How CJ Roy turned Bengaluru’s fringe into fortune
- Video of Bengaluru cop caught red-handed taking Rs 4 lakh bribe goes viral
- Who was Confident Group chairman CJ Roy? Kerala-born entrepreneur, philanthropist and luxury car aficionado
end of article
Trending Stories
- Ind vs NZ: India strike early as Arshdeep Singh removes Tim Seifert
- Budget 2026: Top 5 income tax expectations of salaried, middle class taxpayers
- WWE Royal Rumble 2026: Full match card, predictions, main event, 30th entrant in Men's Battle Royal, and more
- UGC NET December Result 2025 Live Updates: NTA to release scorecards soon, check how to download, more details
- TNTET 2025 result declared at trb.tn.gov.in: How to check scores, cut off, PDF download steps
07:21 How Confident Group chairman CJ Roy’s final hours unfolded at his Bengaluru office amid Income Tax searches: ‘He kept his briefcase with pistol and documents always close to him’- Drama erupts! 'Nahi khelenge': Ex-Pakistan star's explosive take on India-Pakistan World Cup final
Featured in city
07:21 Confident Group chairman CJ Roy had 1.3M Instagram followers: High-end cars, chopper rides, travel stories- Inside Confident Group chairman CJ Roy’s luxury car collection: 12 Rolls-Royce, Bugatti, Lamborghinis and more
- Video of Bengaluru cop caught red-handed taking Rs 4 lakh bribe goes viral
- 22-year-old crushed to death by concrete slab while shooting reel at under-construction flyover in Bareilly
- Confident Group chairman CJ Roy's death: Karnataka minister Priyank Kharge calls it ‘case of pure harassment by IT officials’
- Suspicious material explodes in Karnataka's Bidar: 6, including 4 children, injured
Photostories
- Which countries have no forest cover, and why?
- Taylor Swift’s most loved stage looks ever
- How to stay calm around people who provoke you, as per psychology: 5 effective tips
- How to ensure build a home which remains cool in summer and warm in winters: 5 cost effective tips
- Virat Kohli’s Instagram disappearance to Arijit Singh’s retirement: Top social media buzz makers of January 2026
- 10 famous foods from Bengal that define the cuisine
- 7 workplace red flags that don’t seem like warning signs at first (But shouldn’t be ignored)
- 7 types of tiles for your bathroom and which one is the best
- 8 store-bought snacks and drinks you can make at home
- Trichy Airport Expansion: Longer Runway, New Bridges & Modern Facilities
Videos
04:39 Pakistan Shifting Terror Blame To Kashmiris Through Proxies, Says EFSAS Director06:26 Jaishankar Highlights Gaza As Key Concern At 2nd India–Arab Foreign Ministers’ Meeting03:18 1,279 Modern Buses, Online Tickets & QR Payments: Punjab Public Transport Gets Digital Makeover06:58 Grammy winner Chandrika Tandon sings Vande Mataram at India UN event05:17 'One Power Or Two Powers Can't Solve...': UN Chief Advocates For Multipolarity, Cites India-EU FTA05:17 'Result Of Corruption': Amit Shah Blames Mamata Govt For Anandpur Momo Factory Fire06:29 'Two-Way Bridge' For Innovation: French Envoy Laurent Bili, Ambassador Kwatra Laud India-EU FTA05:48 India Appreciates United States' Efforts At UNSC For Addressing Gaza Issue, Condemns Terrorism07:21 Confident Group Chairman CJ Roy Allegedly Shoots Himself Dead At Bengaluru Office Amid IT Raids
Up Next
Start a Conversation
Post comment