City’s 24/7 water supply project expected to be completed by March 2027
Mangaluru: The Jalasiri 24/7 Mangaluru water supply project is expected to be completed by March 2027, said officials on Friday.
The Rs 617.2 crore critical water supply infrastructure project is being implemented by Karnataka Urban Infrastructure Development and Finance Corporation (KUIDFC), and was awarded to a joint venture agency of Suez India Ltd and DRS Infra Tech Pvt Ltd.
The project started in 2019, was expected to be completed in May 2023, but was delayed owing to Covid. So far, 76% of the works have been completed including the water treatment plant in Adyar.
According to officials, based on the estimated 2020 population of 5,71,249, including Panambur industrial area, NMPT, MCF and DKMU, the city’s water demand stood at 160.3 MLD, including 20% losses. However, the project has been designed to meet demand for the next 30 years. They stated that by 2031, the demand is projected to reach 213.1 MLD, and by 2046 it is expected to rise to 276.7 MLD.
The officials highlighted that the entire city gets covered under the threee master balancing reservoirs (MBRs) at Padil, Bendoor and Panambur, and for the project divided Mangaluru city into 54 zones.
According to officials, so far 85.8% of the clear water transmission mains (CWTM) work has been completed, while the distribution network has reached 74%. Work on overhead tanks (OHTs) stands at 88%, and ground-level service reservoirs (GLSRs) have achieved 95% progress. The installation of intermediate pumping stations (IPS) is 80% complete.
In the house service connections (HSC), 38,200 connections have been completed out of the total planned 95,000, achieving 40.2% progress. Officials noted that authorisation has been granted only for 82,849 connections so far, against which the progress stands at 46.1%.
The project also includes a 125 MLD dissolved air flotation and filtration (DAFF) technology-based water treatment plant at Adyar, which officials described as a first-of-its-kind in India. It has reached 50% completion, while road restoration works are almost complete at 99% .
The officials added that the entire city will be covered under three master balancing reservoirs located at Padil, Bendoor and Panambur, and that Mangaluru has been divided into 54 zones under the project.
The officials also added that in Panambur almost all works are completed and 4 km is pending, while in Bendoor and Padil, 50% and more than 80% works respectively are completed.
On Friday, officials took a media team to the GLSR( Ground level service reserviour) cum OHT (over head tank) project site in Kodikal.
The project started in 2019, was expected to be completed in May 2023, but was delayed owing to Covid. So far, 76% of the works have been completed including the water treatment plant in Adyar.
According to officials, based on the estimated 2020 population of 5,71,249, including Panambur industrial area, NMPT, MCF and DKMU, the city’s water demand stood at 160.3 MLD, including 20% losses. However, the project has been designed to meet demand for the next 30 years. They stated that by 2031, the demand is projected to reach 213.1 MLD, and by 2046 it is expected to rise to 276.7 MLD.
The officials highlighted that the entire city gets covered under the threee master balancing reservoirs (MBRs) at Padil, Bendoor and Panambur, and for the project divided Mangaluru city into 54 zones.
According to officials, so far 85.8% of the clear water transmission mains (CWTM) work has been completed, while the distribution network has reached 74%. Work on overhead tanks (OHTs) stands at 88%, and ground-level service reservoirs (GLSRs) have achieved 95% progress. The installation of intermediate pumping stations (IPS) is 80% complete.
In the house service connections (HSC), 38,200 connections have been completed out of the total planned 95,000, achieving 40.2% progress. Officials noted that authorisation has been granted only for 82,849 connections so far, against which the progress stands at 46.1%.
The officials added that the entire city will be covered under three master balancing reservoirs located at Padil, Bendoor and Panambur, and that Mangaluru has been divided into 54 zones under the project.
The officials also added that in Panambur almost all works are completed and 4 km is pending, while in Bendoor and Padil, 50% and more than 80% works respectively are completed.
On Friday, officials took a media team to the GLSR( Ground level service reserviour) cum OHT (over head tank) project site in Kodikal.
Comments
Be the first to share a thought and become theFirst Voiceof this News Article
end of article
In Mangaluru
- Kasaragod students seek inclusion in Karnataka’s free bus pass scheme
- MU will recall its staff if Kodagu University agrees
- Trekker who sustained leg fracture at Gadaikallu rescued
- Motorcyclist killed after being run over by tipper truck
- Man duped of Rs 5.7 lakh in loan scam
- Renotification of e-auction for defunct liquor licences soon
- NRAI launches Mangaluru, western Karnataka chapter
Featured In City
- As heatwave raises fire risk, Centre issues electrical safety alert after fatal short-circuit incidents
- TMC to move Calcutta high court against Ritabrata Banerjee's recognition as LoP
- UP Electricity Regulatory Commission imposes penalty over delayed power restoration for prepaid smart meter consumers
- Silent protest at Cottage Emporium as Covid salary dues linger
- How Bhopal's big cats survive inside an expanding Indian city
- For decades, 24 out of MP's 26 sanctuaries await notification
- Delhi hotel fire: Owner Lovkesh Bajaj's earlier arrest over Indian IDs for Bangladeshis under lens
Photostories
- Which lucky charm should you place on your office desk; based on your date of birth?
- 8 everyday habits that build strong problem-solving skills in kids
- Sonakshi Sinha and Zaheer Iqbal's penthouse is a relaxing abode of minimalism with bright bohemian colours: Art inspirations to steal
- 8 parenting habits that help kids become independent thinkers
- Which plant should you bring home for the positive vibes; based on your birth date
- 7 locations in India where smart city initiatives are reshaping real estate
- 9 iconic snakes of India's Western and Eastern Ghats
- Pediatrician shares 6 common household items that make many children land up at emergencies
- From Shah Rukh Khan to Kareen Kapoor Khan: 7 parenting lessons to learn from Bollywood celebrities
- 6 signs a working woman is doing well with money
Videos
04:02 Three Civilians Killed, Seven Houses Torched In Suspected Militant Attack In Manipur04:09 Mohali Woman Stabbed To Death By Ex-Partner At Workplace; Accused Attempts Suicide04:21 Putin Says US Pressure On PM Modi Is 'Useless', India-US Ties Won't Affect Russia Relations03:39 PM Modi-Rodriguez Talks Signal India's Push For Long-Term Energy Partnership With Venezuela04:48 India And UK Deepen Strategic Ties As Yvette Cooper's Maiden Visit Delivers Key Agreements06:38 RBI Maintains Repo Rate At 5.25%, Flags Inflation Threats And Lowers FY27 Growth Projection To 6.6%04:48 'I Like Modi A Lot': Trump Signals Breakthrough In India-US Trade Negotiations | Watch03:23 Allies Drift Apart As I.N.D.I.A Bloc Battles Splits, Exits And Leadership Questions | Watch03:31 'DKS Promised Me': Ramalinga Reddy Quits As Cabinet Row Rocks Congress
Top Trends
Up Next
Follow Us On Social Media